Monday, December 29, 2008

Day 8,9,10


The last few days have been spent jacking up the back bedroom, and replacing termite infested studs, joists, and subfloor. Its been a long consecutive work week. (one day off for christmas) and I am very happy with what we have accomplished. As early as next weekend, we can start putting up gypsum, and texturing the walls. Next saturday I am having the shower heads raised for a 6' 4incher, so I dont have to bend over to get my hair wet. Then we can start rebuilding my cabinets and counters. More pictures later.